Stop in for a cup of coffee

Making some more progress on my "Man Cave".
Over the last week, I have gotten all of the electric, phone (4 pair CAT5) and data lines (4 pair GigaSpeed), and tv coax installed.
I have the back wall sheeting installed.
Shawn (spl440) came up today and helped me get the windows and all of the shop side sheeting hung.

Here are a few photos of the progress:
View attachment 1714936539


Me Lifting sheeting for interior walls of the room.
View attachment 1714936544

View attachment 1714936545

Lookin good... :thumbsup: