Thank you Kim. The V/B was sent back to Turbo Action for inspection. And a pump in better condition was sourced. looking at the 727 rebuild book I'm unable to locate an end play measurement for the planetary stack. Is there a spec that should be inspected, before the unit is reassembled? The flow diagram seems to indicate that the output shaft is charged through the front planetary and through the governor valve. Don't want to miss anything.
Forgot to add, the valve body that was built by Turbo action may have been a post 75-77 unit if that matters.

Thanks for the help.