1 day shower ad's

I have worked side by side with a professional remodeler on a few simple bathroom jobs. It takes a good two weeks to cut out, repair, re-frame, re fixture, replumb, rewire etc..no tiling. no flooring.
Then the drywaller does his thing on top of that,
Then the painter,
Then the flooring guy,
Then we come back and fix what they fubarred.
Sometimes, in the interest of expedience, we did it all. But man, that gets expensive. Time is money, and the boss is then on a tight schedule, we work long hours and the billing reflects that. I made good coin.
So yeah, it can go to a month from start to finish, two guys, one Pro, one experienced (I done a few on my own), and depending on choreographing the other tradesmen.
I did a peel and stick on one job, for myself; never again.

I'm retired now, so unless you got something I want, I'm done doing that.